The prime objective of my career is to achieve self-satisfaction through significant contribution, honesty, quality work with high professionalism and dedication towards my employer. It would be my earnest endeavor to ensure exemplary devotion in performing my duties and responsibilities by excelling through teamwork and innovative ideas for achievement of higher performance.
Experienced NDT Technician with knack for identifying and solving complex issues. Known for enhancing inspection processes and improving safety standards. Recognised for contributing to team success and maintaining high-quality control.
Skilled technician with focus on non-destructive testing across various industries. Capable of identifying and resolving potential issues through advanced NDT techniques. Committed to ensuring safety and quality compliance using comprehensive understanding of industry standards and procedures.
Offering strong foundation in technical skills and safety protocols, combined with keen problem-solving abilities and collaborative approach. Knowledgeable about quality control and inspection processes, with hands-on experience in various industrial environments. Ready to use and develop communication, attention to detail, and analytical skills in ANDT role.
Hardworking product testing professional with extensive experience delivering quality, conformant products to specifications. Grades and classifies products accurately with meticulous attention to manufacturing requirements. Collaborates with team members for outstanding productivity levels.
SAFCO (IBB) Sep 2022 – Oct 2022
This project involved Inspection of Exchangers in the utility unit of the plant in Safco IBB I was assigned to perform Tube inspection for the Exchanger, & Fin fan Coolers Team Members : 12
PLANT SHUTDOWN ( SABIC) Nov 2023 – Dec 2023
The shutdown was for the Hydrocarbon unit of the plant and we were responsible for the Inspection of Exchangers. Our job was to perform (ECT, REFT&MFL) a method This technique was trained to us by a Eddy technology Which have the expertise in this fic Team Members : 14
SHARQ SHUTDOWN Feb 2024-Mar 2024
In this shutdown I worked as an lead technician for tube inspection and I have performed ECT, REFT&MFL in this shutdown nearly 10-15 Exchangers was inspected and final report was done by me Team Member : 12
SHIPCHEM SHUTDOWN Apr 2024 -May 2024
The project was Handed over to us by Shipchem and this project consisted of inspection for 3 units This project included various Ndt activities such as visual inspection, conventional Ndt, Radiography, and Tube Inspection I was a part of the Tube Inspection Team which consisted of Two shift day and night and I was the one who lead the night shift team for inspecting the exchanger Team Members : 20
SAFCO (ALBROYN) SHUTDOWN Jun, 2024 - Jul, 2024
These were two different units Ammonia and Utility in nearly 50 Exchangers was offered to our company I have assisted in this project to my fellow colleague The learning path in this project was how to coordinate team and to work more effectively As per our client requirements ECT,REFT& MFL this technique was held and we found some leaks in some Exchangers without any flaws we successfully completed that shutdown within the given time period Team Members : 14
YASEERF Aug 2024
There was an job in YaseerF, As per our client requirement MFL Tube inspection need to be done for two Exchangers I was an Lead technician to perform MFL in that Exchangers The given time period was only four days 50 percentage of exchanger need to be inspected overall tube account for each Exchanger was 2150 we did that job efficiently and we completed successfully and some wall lose was dected by our team Team Members : 4
PETROCHEMKYA SOUTH Sep 2024
A job was offered to us need to inspect tube replaced in the exchanger it wasn’t used for two year after the replace of tube in the exchanger it was yard for the long time so they planned to install that bundle so for the client clarification they ask us to perform inspection in that, I performed MFL in that exchanger it was only three days job Team Members :4
YASEERF Sep 2024
A two exchanger need to be inspected As per client requirement MFL need to be done In that exchanger some leak was there so the client need percentage of the defeat Inspection was held successfully we found out leaked tube and it was 40 percentage of wall loss Team Members : 8, SHIPCHEM Oct 2024 One Boiler exchanger was offered to us as per the client requirement IRIS need to be done But we faced some difficulties to perform IRIS the manhole was small so we are not able to perform IRIS but any how we did that job I did Borescope and also I was assisting my team for IRIS Team Members :3,
YASEERF Nov 2024-Dec 2024
It was Turn around we did various techniques like ECT, REFT&MFL As per our client requirement we did all the above technique This Turn around was for 45 days Our us they offered 100 exchangers all the exchangers was inspected And I was the one Coordinating the night shift crew and reporting the update status to client and submitting the completed exchangers report Team Member:16
NATPET (YANBU) Jan 2025
It was Turn around we did various techniques like ECT, REFT&MFL As per our client requirement we did all the above technique, SABTANK (SABIC) Mar 2025 A job was offered to us need to inspect tube replaced in the exchanger it wasn’t used for two year after the replace of tube in the exchanger it was yard for the long time so they planned to install that bundle so for the client clarification they ask us to perform inspection in that, I performed MFL in that exchanger it was only three days job
BAPCO (BAHRAIN) May 2025
It was Turn around we did various techniques like ECT, REFT,MFL&IRIS As per our client requirement we did all the above technique This Turn around was for 25 days Our us they offered 15 exchangers all the exchangers was inspected And I was the one Coordinating the night shift crew and reporting the update status to client and submitting the completed exchangers report
YANPET (SABIC) Jun 2025
It was Turn around for POLYMER UNIT we did various techniques like ECT, REFT&MFL As per our client requirement we did all the above technique, SABTANK (SABIC) Sep 2025 A job was offered to us need to inspect tube replaced in the exchanger it wasn’t used for two year after the replace of tube in the exchanger it was yard for the long time so they planned to install that bundle so for the client clarification they ask us to perform inspection in that, I performed MFL in that exchanger it was only three days job,
YANSAB (SABIC) Oct 2025
A job was offered to us need to inspect tube in the exchanger it wasn’t used for two year after the replace of tube in the exchanger it was yard for the long time so they planned to install that bundle so for the client clarification they ask us to perform inspection in that, I performed MFL in that exchanger and another exchanger was offered for RFET
IBN RUSHD (SABIC) Oct 2025
It was Turn around we did ECT As per our client requirement for two condenser ,They were very hurry to finish the shutdown they gave only limited time with in two days we completed that as per our client request.