Sweden for Installation & Commissioning of Software/Hardware of Tarbela in plant S.P.I.D.E.R SCADA System, Which Have Two Front Ends (FE-200), Three Work Stations (WS – 200), 11 No
Remote Terminal Units (RTU- 400), Printers etc
This SCADA System Have 5000 Indications (Double and Single), Measurands (Measured Values), 200 regulation Objects, 250 Accumulated Values (Energy Values), 1000 Display Catalogue & 7000 Display Data
Now-a-days Tarbela Power Station 1 & 2, Having total Capacity of 3478MW is controlled and Supervised by this In - Plant SCADA System
I Also Supervised the Installation and Commissioning of Hardware equipment i.e.68000 Micro Processor based Front Ends (FE-200), Work Stations (WS – 200), Tesselators (8020) and 20" Color VDUs
I was deputed by WAPDA Tarbela as project Manager (Software/Hardware Engineer) to take Part/supervision for the Completion of warranty Period of SCADA System, Which Started with Effect from MAY 10, 1995 and successfully completed on May 10, 1997 (Two Years)
Also Have Sufficient Practical knowledge of System and Personnel Computers, Windows, MS Word, Excel, DOS, and VAx VMS Operating Systems as Well
Supervised the Installation and Commissioning of in plant ABB S.P.I.D.E.R SCADA (Software/Hardware) equipment i.e
RTU 400, 68000 Micro Processor Front Ends (FE-200), Work Stations (WS – 200), Tesselators (8020) and 20" Color VDUs.
Projects Manager
Marine Services Company Limited
Jeddah
11.2017 - Current
Prepares technical correspondence, reports and studies including systems studies for projects
Monitoring project progress and quality of work to ensure successful project completion
Managing engineering project team communication, including communicating objectives for critical milestones, budget, schedule and customer satisfaction for project team members
Enhancing and maintaining relationships with internal groups, external sub-contractors and clients and suppliers
Writing and planning project scope, action plans, proposals, cost estimates, change notices and budgets
Provide support to the development of schedules, business proposal, risk registers, procurement strategies, design plans and quality plans in the early stages of projects
Witness electrical testing, pre-commissioning, commissioning, and start-up activities
Monitor construction of electrical installation and testing activities
Implementations of QHSE rules at project sites and MSCL workshop for safety of men and materials
Testing and commissioning Engineer i.e
Testing and commissioning team leader for capital projects of GTS, Crude oil treatment plants, fuel unloading stations and firefighting systems successfully commissioned and handed over to SEC – SOA Sharourah, Najran and Tihama Power Plants
Provides technical support during pre-bid phase, technical proposal evaluation phase, and post-award phase, execute phase and testing and commissioning phases for Projects
Participates in the technical evaluation of potential bidders for contracts on assigned projects
Coordinates the technical analysis and evaluation of bids proposed
Prepares technical correspondence, reports and studies including systems studies for projects
Follows quality control and quality assurance procedures established by management
Knowledge of computers and basic software applications: MS Office (Word, Excel, Power Point) etc
Supervises discipline staff that are in subordinate positions
Monitoring project progress and quality of work to ensure successful project completion
Managing engineering project team communication, including communicating objectives for critical milestones, budget, schedule and customer satisfaction for project team members
Enhancing and maintaining relationships with internal groups and clients
Fully involved in testing, commissioning, construction and maintenance activities of electrical equipment
Evaluating equipment for suitability as per site and standard requirements.
Generation Engineering Specialist
01.2016 - 11.2017
Grade -52) Electrical and instrumentation, Quality and Performance Divisions Saudi Electricity Company SOA – Abha head office KSA
Ex SEC Computer No
54129
GTSD – SOA Quality & Performance Division:
Audit policies and Power plants audits.
Saudi Electricity Company
01.1997 - 01.2017
Reason of leaving SEC:
Resignation due to suffering of children education as children were getting education in Pakistan international school Jeddah.
03.2007 - 01.2009
Took part G.E in Installation & Commissioning of Five Fiat TG 20 (B7/8) Gas Turbines “22.5MW” Control System retrofit with G.E MKVIE USA Turbine Control
Took part in retrofitting of FIAT GTs with excitation system EX2100
Took part in integration of all I/Os and site acceptance tests of Five G.E Gas Turbines (G.E FR-7 5x 51.5 MW) and Five Fiat TG20 B7/8 “5x22.5MW”, BOPs and firefighting systems I/Os interfaced with Central G.E MKVIE Distributed control system as well as integration of all other I/Os of allied Auxiliaries of total plant with Central DCS.
Shift Engineer
11.1997 - 03.2007
Shift in Charge) at SEC SOA Najran power plant of 5x22.5Mw (Fiat TG-20 B7/8 GTs) and 5x51.5MW (G.E Fr - 7 Mark – V, VI & VIe Frame 7 GTs) of total installed capacity of 370MW
Najran Power Plant BOPs (Balance of Plants), Crude oil (Alfa Laval) and distillate treatment plants, steam boilers, hot water boilers, Fire Fighting systems, 2.5 MVA and 5 MVA Blacks Start Diesel Generator Sets
Load Regulation, monitoring, controlling of all these Gas Turbines, allied auxiliaries and BOPs are now controlled & supervised by G.E MKVIe Distributed Controlled System (DCS).
System administrator, Software/Hardware Engineer
R SCADA, MW Hydel Power Station
Tarbela
05.1997 - 11.1997
The below mentioned system fully taken over and worked as, of in plant S.P.I.D.E
Project Manager
01.1994 - 05.1997
Pakistan Water
01.1988 - 01.1997
Power Development Authority (WAPDA) 9 years from
Supervisory Shift Engineer
04.1993 - 01.1994
WAPDA Combined cycle Kot Addu Power Plant Pakistan:
(12 x 100 MW combined Cycle Gas Turbine (CCGT) Power Station Kot Addu Pakistan)
Operation/Supervision of 11KV/132KV/220KV (SF6, OBCs and ABCBs) Switchgears & Supervision/Operation of Machines through Speed Tronics Control KWU (V94.2), TG50 Gas Turbines, HRSGs & STGs (Steam Turbine Generators) and all other allied auxiliaries
I also supervised the Operation and Weekly Testing of Fire Fighting Station at 12X100MW Combined Cycle Gas Turbine Power Station Kot Addu, Pakistan.
Operation Engineer
07.1988 - 04.1993
(12x100 MW Combined Cycle Gas Turbine (CCGT) Power Station Kot Addu Pakistan)
Operation/Supervision of 11KV/132KV/220KV (SF6, OBCs and ABCBs) Switchgears & Supervision/Operation of Machines through Speed Tronics Control KWU (V94.2), TG50 Gas Turbines, HRSGs & STGs (Steam Turbine Generators) and all other allied auxiliaries
I also supervised the Operation and Weekly Testing of Fire Fighting Station at 12X100MW Combined Cycle Gas Turbine Power Station Kot Addu, Pakistan.
Ahmad
Nationality
- 02.1965
Transferable
Permanent and personnel
E mail: ahmadjanlala@gmail.com
Mobile: 00966502755734
Total Experience to date: 33+ years.
Education
B.E - Electronics
NED University of Engineering and Technology
F.Sc (H.S.C - Pre-Engg
Islamia college
Matric (S.S.C) - undefined
Accomplishments
QA/QC audit for CEMS (Continuous Emission Monitoring System)/GLEMS (Ground Level Emission Monitoring System) of Environmental projects of power plants
Commissioning of CEMS/GLEMS at SEC SOA power plants
Audits of power plants capital projects during and after executions
Team leader for Prequalification of bidders for operation, Electrical, Mechanical repair and manufacturing jobs
Study and Compilation of SGT6-2000E Training courses for nominees of all SEC operating areas
Witnessing of contractor’s quality control inspections to ensure that the project works are constructed as per the applicable codes, standards, approved drawings and specifications
Participated in the technical evaluation of potential bidders for contracts on assigned projects, and in recommending shortlists of qualified contractors
Coordinated the technical analysis and evaluation of bids proposed
Preparation of Scope and implementation with 3rd party for the work of contract for QMS "ISO 9001: 2015” certification for operation, maintenance & technical support sections of SEC SOA Asir power plant and finally got certification of "ISO 9001: 2015” for SEC SOA Asir Power Plant
Preparation of action plans for remaining power plants of SEC SOA for certification of "ISO 9001: 2015”
Preparation of complete documents for "ISO 9001: 2015”
From August 2015 to January 2016:
Worked as Generation engineering specialist at GTSD SEC – SOA Abha Electrical & Instrumentation Division:
Follow up of ongoing capital projects of the power plants like firefighting, control, Electrical, Mechanical and environmental projects like CEMS (Continuous Emission Monitoring System)/GLEMS (Ground Level Emission Monitoring System) etc
Witnessed electrical testing, pre-commissioning, commissioning, and start-up activities for power plant auxiliaries
Monitor construction Contractor’s electromechanical installation, testing and commissioning activities
Prepared scope of work for many capital projects like:
Scope of work for Jezan "Replacement of GT # 10 & 11 480V Switchgears."
Scope of Work for replacement of the HMI system of units (GE MKVIe) from 21 to 25 and the unit 16 in Jezan power plant
Scope of work for additional fuel skid for GT # 7 & 8 Jezan Power plant
From January 2009 to August 2015:
Saudi Electricity Company, Najran Power Station (Installed Capacity of 541MW)
Worked as Technical Support Engineer in Technical support section of SEC SOA NPP
Dealing with preparation of Scope of work for Mechanical, Electrical, control system, firefighting up gradation, short form and long form contracts, tendering, kick off meetings, job explanation meetings with contractors and implementation of SOWs by contractors at site start from design & Engineering, Material procurement and till installation testing and commissioning of the projects like to date:
Successful completion of the projects like rehabilitation of Exhaust system of FIAT and GE FR- 7 GTs
Water treatment plant
Station air compressors control system retrofit
Fire and safety projects
Control system retrofit for fuel treatment plants
Diesel pumps
Black start diesel generators, engines, fuel tanks firefighting system modification and rehabilitation of soft water tank and Digital fuel flow meters for GTs and Fuel Unloading Station
Provided technical support during pre-bid phase, technical proposal evaluation phase, and post-award phase of all power plants Projects
Preparation of service orders through SAP system as per contracts, maintaining budget and issuing Job completion certificates/Service entry sheets after successful completion of the projects by contractors
Comprehensive data preparation for project “Turbine Inlet Air Cooling System (TIAC) for 5 G.E Gas Turbines at Najran Power Station
Technical Answers for Bidders for pre - bid clarifications for project “Turbine Inlet Air Cooling System for 5 G.E Frame 7 Gas Turbines at Najran Power Station
Preparation of Scope of work for Short form projects like Black Start Diesel Generator set major overhauling, Steam Boilers, crude oil treatment Plants control system retrofit, water treatments, Firefighting systems, Fuel tanks Cathodic protections, GE Frame – 7 GTs Exhaust System Repair at Najran Power Plant
Technical study and implementation till testing and commissioning for scope of work for of First, second, 3rd and 4th stages of improvement of firefighting systems
Fully involved in Power Plant Project of “Phase – I, II & III at Najran Power Plant as Built Drawings preparations” for (Collection & Documentation of existing Drawings data of Power Plant for preliminary Survey
Submit detailed report of survey) as under
General layout of site
Basic Management Course at WAPDA Academy Tarbela (6 Months)
Technical Training at WAPDA Engineering Academy Faisalabad (6 Months)
Power Generation, Transmission, Grid System Operation (GSO) and Power Distribution
Gas Turbine Operation and Maintenance Training at WAPDA Gas Turbine Training center Faisalabad Pakistan (6 Months)
On Job Training at 12X100MW Combined Cycle Gas Turbine Power Station WAPDA, Kot Addu Pakistan
MPM (Measuring Processing and Monitoring) Training at 3500 MW Tarbela power station
(1 Month)
Joint Control Training at Tarbela (15 Days)
Micro Computer Training at Tarbela (10 Days)
Course on Advanced Computer Concepts from WAPDA Engineering Academy Faisalabad
Fuel Oil Treatment Plant (Alfa Laval Operation Training at Najran Central Power Station, Kingdom of Saudi Arabia)
SAP system trainings at SEC SOA trainings center Abha KSA
ISO 9001: 2015 QMS Training at SEC SOA KSA
IRCA registered training by M/s QCB at Abha KSA
Introduction to Occupational Safety and Health course with exam passed
Essentials of Occupational Safety and Health course with exam passed
Blood borne Pathogens in Workplace course with exam passed
Soft Skill:
Excellent oral and written communication skills
Ability to multitask as well as cope with the deadlines
Creative and innovative to provide solutions that meet the project
Diligent in following work process, industry standards and procedures
Persistent with problem solving until the problem is resolved
Team player on making decisions on what is the best for the company.
Affiliations
Consultant member of SCE (Saudi Council of Engineers).
Member of Pakistan Engineering Council.
Member of IEEE Pakistan.
5