Organized and dependable candidate successful at managing multiple priorities with a positive attitude. Willingness to take on added responsibilities to meet team goals. Committed to providing accurate work with eye for detail. Consistently commended for meeting stringent project deadlines under budget.
Overview
16
16
years of professional experience
5
5
years of post-secondary education
1
1
Certification
Work History
Senior Mechanical Construction Engineer
PETROJET (HAWIYA ENIZAH GAS STORAGE RESERVIOR )
ALHASSA, SAUDI ARABIA
02.2023 - Current
Well study project challenges for preparing constructability plan
Responsible for piping erection and welding activities
Follow up and managing daily productivity as per project schedule
Supervise site activities to be sure that work follows ARAMCO safety regulation
Raise daily and weekly follow up reports to construction manager including recommendation and obstacles
follow up Dia. inch welded and pipe support installation every day and how we can improve progress .
follow up and push finishing sub systems and systems by cleared all required punch to be offered for hydrotesting
follow test package reinstatement to reach PMCC
Senior Mechanical Construction Engineer
PETROJET (SHDQM STEAM TURBINE GENERATOR ) ARAMCO
ABQAIQ, SAUDI ARABIA
12.2020 - 02.2023
Managing & planning all mechanical activities also manpower and equipment flow during project life time
Well study project challenges for preparing constructability plan
follow up & managing procurement cycle during project by giving priority as per site requirement and constructability to avoid work stop or double work.
Managing & follow-up all fabrication activities (piping ,pipe support ,steel fabrication ) and make sure that all activities meets Aramco (SAES) standard and safety regulation and also as per approved procedure.
Managing & follow-up equipment (static &rotating) erection starting from route survey ,lifting plans ,cranes setup ,required permits and approved certified tools, manpower till final erection and inspection.
Coordinated labour and construction materials to ensure site met targets outlined in production program.
Well study project challenges for preparing constructability plan
Strategically deployed construction staff to maximize productivity.
Responsible for piping erection and welding activities
Follow up and managing daily productivity as per project schedule
Supervise site activities to be sure that work follows ARAMCO safety regulation
Raise daily and weekly follow up reports to construction manager including recommendation and obstacles
follow up Dia. inch welded and pipe support installation every day and how we can improve progress .
follow up and push finishing sub systems and systems by cleared all required punch to be offered for hydrotesting
follow test package reinstatement to reach PMCC
Senior Mechanical Construction Engineer
PETROJET (Hydrogen dioxide plant )(oxygen plant)
cairo, Egypt
02.2017 - 02.2019
Managing & planning all mechanical activities also manpower and equipment flow during project life time
Well study project challenges for preparing constructability plan
Inspected completed equipment for compliance with codes, design specifications and quality standards.
follow up & managing procurement cycle during project by giving priority as per site requirement and constructability to avoid work stop or double work.
Managing & follow-up all fabrication activities (piping ,pipe support ,steel fabrication ) and make sure that all activities meets Aramco (SAES) standard and safety regulation and also as per approved procedure.
Managing & follow-up equipment (static &rotating) erection starting from route survey ,lifting plans ,cranes setup ,required permits and approved certified tools, manpower till final erection and inspection.
continuous supervision and raise daily report to top management
Senior Mechanical Construction Engineer
PETROJET (Oil & gas refinery project )(ERC)
CAIRO, EGYPT
03.2014 - 03.2017
Managing & planning all mechanical activities also manpower and equipment flow during project life time
Well study project challenges for preparing constructability plan
Inspected completed equipment for compliance with codes, design specifications and quality standards.
follow up & managing procurement cycle during project by giving priority as per site requirement and constructability to avoid work stop or double work.
Managing & follow-up all fabrication activities (piping ,pipe support ,steel fabrication ) and make sure that all activities meets Aramco (SAES) standard and safety regulation and also as per approved procedure.
Managing & follow-up equipment (static &rotating) erection starting from route survey ,lifting plans ,cranes setup ,required permits and approved certified tools, manpower till final erection and inspection.