A highly seasoned and results-driven Electronic Engineer (B.Sc.) with 27 years of progressive experience in the construction, installation, testing, and commissioning of EHV/HV electricity substations, Regional Control Centers (RCCs), and Distribution Control Centers (DCCs). Proven success in leadership roles, including 13 years as Site Manager and Senior Site Manager, managing large-scale, fast-track, and complex EPC projects up to $500 million. PMP-certified with a deep commitment to quality, HSE compliance, and on-time project delivery. Seeking a challenging role to leverage extensive technical knowledge, managerial decision-making abilities, and strong team-building skills to drive project success.
Overview
27
27
years of professional experience
1
1
Certification
Work History
Senior Site Manager
DNV Energy
04.2025 - Current
Oversight of the construction, engineering, installation, testing, and commissioning of complete SEC-SDCC Buildings, including architectural, structural, electrical, mechanical, and special systems works.
Project: Smart Distribution Control Center (SDCC Project) - Group B (ASSIR, JAZAN, and MADINAH).
Project Construction Manager
Elsewedy Electric T&D
08.2024 - 03.2025
Managed construction execution for this large-scale, high-value, fast-track EPC project.
Project: Tahya Masr Multipurpose Terminal project at Alexandria Port (EPC – Fast Track Project | $500M).
HV Construction Manager
Elsewedy Electric T&D (EETD)
Riyadh
08.2023 - 07.2024
Ensured timely completion and quality of HV substation construction, compliance with HSE/Quality plans, interfaced with functional teams, and managed stakeholder relations.
Provided input for project schedules, ensured daily/weekly short-range planning, monitored productivity, implemented site safety, and managed contractual commitments for field activities.
Project: Lot.2 JICA Project: Upgrading of Distribution Management System and AMI in North Electricity Distribution Company.
Site Manager
Elsewedy Electric T&D
Cairo
10.2021 - 09.2022
Managed all site activities, ensured quality adherence, maintained effective plan for tool/supply control, administered labor policies, and developed/implemented site document control.
Project: Construction of New Regional Control Centre in Delta Zone (DRCC) (SCADA, RTUs, Telecom, New DRCC Building, etc., covering 107 Substations).
Site Manager
GE-Digital
Cairo
01.2021 - 09.2021
Day-to-day coordination with Client/Subcontractors, ensured on-time and in-budget execution, monitored KPIs, enforced EHS/Quality standards, and acted as authorized representative for site matters.
Project: Egypt DCCs Project Alexandria East (Implementation and Construction of EEHC/AEDC'- DCCs Project).
Site Manager
GE Gird Solution
Jeddah
05.2016 - 10.2020
Planned site activities, ensured resource availability, monitored progress, and enforced strict EHS/Quality compliance across multiple concurrent substation projects.
Followed project time schedules, verified progress, prepared reports, coordinated material/equipment/manpower needs, and managed all site technical and administrative integration.
Projects: New 110/13.8kV Substation at Madinah Islamic University-2, 380kv GIS Expansion at Al-Taif, 110 KV OHTL Replacement by U/G Cables.
Senior Project Engineer
Al-Fanar Construction Company
Jeddah
03.2007 - 01.2011
Acted as PM representative in meetings, coordinated between design consultant/client, prepared correspondence and purchase requests, and managed bill of quantities/project material requirements.
Projects: New Kandarah 380/110/13.8 KV S/S, New Thuwal 380/110/13.8 KV S/S.
Site Engineer
AREVA Egypt
04.2005 - 03.2007
Supervision of construction (Interface/RTU cabinet installation, cable laying/termination), pre-commissioning (offline/global/point-to-point tests), and test signal verification.
Project: West Delta RCC
Site Engineer
TEC Engineering, SIEMENS
Cairo
08.2001 - 03.2005
Supervision of construction and pre-commissioning activities for Cairo RCC; engineering of C&I systems for 300 MW & 2x150 MW TPS Upgrade.
Project: Cairo RCC / ATAKA TPS
Site Engineer
TARRADCO CO
Alexandria
09.1998 - 08.2001
Complete supervision for construction, installation, cable termination, pre-commissioning, and global testing of signals from the substation to the control center.
Project: Alexandria RCC
Education
Bachelor of Science - Electronic Engineering
Faculty of Electronic Engineering
05.1998
Skills
Project Management
PMP Principles
Stakeholder Management
Budget Adherence
Resource Allocation
Schedule Development/Monitoring
Site Administration
Technical Expertise
EHV/HV Substations (GIS/AIS)
Regional/Distribution Control Centers (RCC/DCC/SDCC)