Resourceful Project Manager with 19 years of expertise in organizing business operations, financial oversight and resource management to achieve smooth flow and project operations. Leads procurement of resources including equipment and supplies. Monitors projects by adhering to production schedule and budget, managing production team, identifying problems and providing targeted solutions. Knowledgeable in accounting principles, bookkeeping, budget and financial management.Team leader committed to improving customer satisfaction. Skilled at policy implementation, strategic planning and staff governance. Listens to customers to understand needs and optimise service delivery.
Project: Dallah Business building
Finishing and MEP work for the B2 building, a five-floor structure spanning 15,000 square meters. This project is of utmost importance, as it involves turning the key to success in terms of completing the necessary tasks. The scope of work encompasses various aspects, including the finishing touches and MEP (mechanical, electrical, and plumbing) work. The B2 building, with its substantial size and multiple floors, requires meticulous attention to detail and expertise in order to ensure its successful completion
Project: MASARAH Retail Mall
The project at hand entails the construction of a two-story building, specifically designed for retail purposes. The building boasts a generous rental area spanning 1200 square meters. Additionally, we have taken into account the need for ample parking space, accommodating up to 80 cars. To ensure the convenience of visitors, we have included a water tank and a designated parking area. Furthermore, our team will diligently carry out the necessary asphalt work and landscaping to enhance the overall aesthetic appeal of the mall
Project: KING ABDUL ROAD DEVELOPMENT PROJECT
(Civil Work for Haramin METRO station)
The scope of work is to supply and install concrete work, for a four-story underground metro station
Including slabs thickness from 1.60 m to 3.50 m depth and 7.80 clear height walls from 1.20m to 2.00 m width.
Project: Citric Acid Plant for Saudi Bio-Acid Company (Consultant- Keir & Associated SA
Scope of Work: Complete Civil and Steel Structure Work Project (Value 250000000 $)
The project contains the following Buildings
1- Main Process Building 7 Floors Steel Structure with an area of 2700 m2 with full Equipment, Tanks, and pumps (Fermenters, Crystallizers, Cookers, etc….).
2- Citric Acid Store Steel Structure Building with an area of 1800 m2.
3- Utilities Building Steel Structure Building area 1700 m2 (chillers, Air Compressors & Cool Pool Tanks)
4- Hazardous Chemical Stores (Dry & Liquid Bulk) area 500m2
5- Raw Water Treatment 2100 m2 with all Filtration Tanks.
6- Water Reservoir with Capacity of 14250 m3
7- Waste Water Treatment Plant.
8- Gas Turbine.
9- Conservancy Tank.
10- Administration Building.
11- Laboratory Building.
Project: Jabal Sayed (HCIS) Mine; Owner-BARIQ Minerals Corp (Australian).
Project Consultant Office-Lavalin SNC Consulting (Australian).
Turn Key Project Contains 6 Areas, My Area was (Area 4) which contains a Guard House Building, Security Building, Shade Canopy (Steel Structure), Transformer Room, Substation Room, Chain Link Fence, and Administration Building.