Leading Mechanical Engineer with strong communication skills, experience managing engineering teams and collaborating with other departments from manufacturing to operations and marketing. Self-starter with proven experience managing projects from concept to completion.
· Responsible for maintenance of cement grinding and packing section including 5 x Ball Mills and 2 x Gypsum Crushers along with Packing section.
· Major maintenance tasks in other areas of the plant.
· Assigning tasks, providing guidance and training to technicians, and ensuring that work is completed according to specifications and safety standards.
· Responsible for scheduling maintenance and repair activities, ordering necessary materials and equipment, and monitoring progress to meet deadlines.
· Troubleshoot technical issues, conduct quality inspections, and communicate effectively with other departments or stakeholders to ensure smooth operations.
· Erection and Commissioning work of Cement grinding and Packing section at Kohat Cement Limited Line 3 Project.
· Erection and Commissioning work of Cement grinding and Packing section at Kohat Cement Limited Line 3 Project.
· Overseeing the installation and assembly of mechanical components, equipment, or structures at a construction site.
· Interpreting engineering drawings, supervising work crews, and conducting quality inspections to ensure that work meets safety standards and quality requirements.
· Manage schedules, budgets, and resources effectively to complete erection projects on time and within budget.
Qassim Cement Company.
1. Commissioning of Loesche 63.3+3 VRM having a designed production capacity of 300 tph.
2. Loesche 63.3 + 3 VRM roller tyres replacement project.
3. Girth Gear Alignment of Ball Mill Unidon 5.2x14 in coordination of FLSmidth expert.
4. Installation of DMGO-25.4 gearbox for cement mill main drive in coordination of Flender expert.
5. Major Overhauling of DMGH-25.4 gearbox in coordination of Flender Expert.
6. Carry out replacement of 6 x slide shoe bearings during shutdown of cement mills.
7. Replacement of Bucket elevator belt utilizing inhouse resources.
8. Atox VRM roller seal and bearings replacement.
9. Clinker crusher rotor and bearings replacement.
Bestway Cement Ltd.
1. Kiln girth gear reversal and alignment job.
2. Cooler ABC inlet replacement project.
3. Ventomatic new packing machine erection work.
4. Cooler EP(ELEX) complete replacement.
5. Kiln thrust roller replacement.
6. Cement mill slide shoe bearings replacement.
7. Silo bucket elevator belt replacement (without Aumund expert support).
Qatar National Cement Company.
1. Pffiefer VRM rollers and pressure frame replacement.
2. Kiln supporting roller and bearings replacement.
3. Gypsum Crusher blow bars replacement.
4. Limestone crusher rotor bearings replacement.
5. Pffifer VRM complete separator rotor replacement.
6. Belt bucket elevator belt replacement.
7. Cement Mill CMD main gearbox overhauling.
8. Hydraulic jacks, pumps, heat exchangers, compressor maintenance.
Industrial Aid Services.
1. Cement mill erection from base level upto final alignment.
2. Main gearbox erection and commissioning.
3. Separator complete erection work.
4. Roller press erection and commissioning work.
5. Mill fans erection work.
6. Belt conveyor structures installation.
Pan conveyor complete erection work