HAPAM disconnectors / earth switches replacement
- - Dismantling of outdoor DS/ES of different voltage levels (380,230 and 115KV).
- - Ensure availability of all cables required for interface.
- - Ensure existing steel structure is properly leveled for perfect DS/ES alignment.
- - Installation of new DS/ES.
- Performing all tests required for operation of DS/ES
Installation and testing of 5 mobile SS - RIYADH
- Connection of LC Cable Plugs to be ready for testing.
- Laying of LV Cables between SWG Truck & TR Truck.
- Laying of MV Cables (SEC Scope).
- Laying & Connection for DC Source.
- Laying & Connection for AC Source.
- Laying & Connection for Grounding Cables.
- installation Gibson Board / Foam for MV Cables Holes.
- Supply & Installation for Cable Glands, Lugs for AC/DC Sources.
- Testing & Commissioning for power & AUX transformer.
- Testing & Commissioning for MV / HV equipment's ( GIS & SWGR).