- Go through the contract agreement before taking up any project to clearly understand the scope of work, manpower required, duration of work, scheduling Level-4 schedules.
- Go through the IFC drawings to know the in and out of the project and Coordinate with the Engineering Dept for any queries.
- Prepare ITP in co-ordination with QA/QC.
- Attend the Kick-off Meeting with the clients-Construction/Projects Manager and put before the Technical Submittals for Approval through QA/QC.
- Arrange contracts with the subcontracts and mobilize manpower at site obtaining the IDs.
- Plan the activities on Level-4 Schedule
- Order all the long lead items at the start of Project as soon as P.O is obtained.
- Order minor equipment like humidifier, exhaust fans, dampers, louvers, duct etc and co-ordinate with the concerned Site Engineer.
- To ensure that the work is completed within time with the given specifications and standards and coordination with all the Eng. Disciplines so that the work flows smoothly and continuously.
- Co-ordinate the sub-ordinates and settle disputes amicably and attend appraisal meetings, classification meetings with site engineers , mangers, sub and main contractors, client in case of delay and dreg, work, unavailability of material and suggest suitable alterations if any.
- Take care of the following activities at site
o Civil openings required at site
o Scoff fold required
o Supports required
o Duct Installations
o Damper installation
o Insulation of duct
o Exhaust fan installations
o Equipment Installations
o Refrigerant piping works with proper support and safety.
o Minor equipment’s – chemical filter, humidifier, bleed fans etc. installations
o Raising inspections for any material including Duct and accessories at Site (RFI)
o Track the progress of project on daily and weekly basis.
- Keenly take up invoices and follow up with the client on a monthly basis.
- Submit the checks to the account department and update the project manager in regards to the project progress and payment received for the concerned project.
- Track the budget and expenses of the project at all times.
- Prepare as-built and hand over documents to close the project
Electrical and Control Works:
- Installation of DDC and MCC panels.
- Check for Cable and other electrical material as per specs (cable size, armored – unarmored, make, etc.)
- Torque and Meggering of cables in co-ordination with QA/QC.
- Installation of Field Devices
- Installation of Isolator switches.
- See for the electrical team to follow Cable pulling schedule
- Meggering and Terminations
- Raise (RFI) for inspections of mechanical as well as electrical installation completion in co-ordination with QA/QC.
- Request the Client for power and schedule TAB and BASS activities. (Start up and Commissioning)