Precise Quality Control Engineer offering 5 years of experience assessing products for defects and training employees on quality control aspects. Committed to working diligently and meeting highest standards of product safety and quality. To seek and maintain full-time position that offers professional challenges utilizing interpersonal skills, excellent time management and problem-solving skills. Hardworking and passionate job seeker with strong organizational skills eager to secure entry-level Electrical Engineer position. Ready to help team achieve company goals. Enthusiastic Electrical Engineer eager to contribute to team success through hard work, attention to detail and excellent organizational skills.
Project: Expansion of Rabigh-2 Powerplant 380KV BSP Substation
Client: NEOM / SAUDI ELECTRICITY COMPANY
• Assure the Quality Standards as per project Specifications.
• Preparation and submittal of RFI.
• Review and Inspection of all Electrical Material (MIR's) prior to installations.
• Daily monitoring the Construction Activities and Raise Surveillance (or) Non-Conformance Report.
• Responsible for Overall implementation of Quality Control related electrical works accordance with project specifications and Engineering Standards.
• Verify the equipment and devices used in project meets the required specifications as per project requirements, standards and tested in accordance with the procedures.
• Monitor the Underground installations; check the required burial depth and spacing requirements to adjacent installations, prior to back filling.
• Inspection of Electrical Installation Panels monitoring control panel wiring, termination, cable routing and cable tray installation.
• Verify all required Inspection Report and test records are systematically generated and compiled according to the QC procedures.
• Coordinate with client representatives regarding the implementation and quality of works.
• Inspection of Switchgear Panel Installation, Cable termination and Bus Bar torque.
• Installation of Control Panel marshaling panels and termination continuity and Megger test.
• Inspection of Ground Rod and Grounding Cable, as per Engineering specification.
• Preparation of Electrical Inspection Reports.
• Inspection of Heat Tracing Panel Installation, PT, RTD junction box installation and heat tracing cable laying and Meggering.
• Provide sufficient feedback to QA/QC manager on the day to day quality issues.
• To supervise and carry out effective implementation of work schedule to clear punch list.
Project: Construction of UML-JOUD GIS Substation BSP 380KV/110KV
Client: SAUDI ELECTRICITY COMPANY
• Assure the Quality Standards as per project Specifications.
• Prepared, documented and executed detailed test plans, test cases and defect reports.
• Preparation of Inspection and test plan, construction quality procedure and method of statement.
• Preparation and submittal of RFI.
• Review and Inspection of all Electrical Material (MIR's) prior to installations.
• Daily monitoring the Construction Activities and Raise Surveillance (or) Non-Conformance Report.
• Responsible for Overall implementation of Quality Control related electrical works accordance with project specifications and Engineering Standards.
• Verify the equipment and devices used in project meets the required specifications as per project requirements, standards and tested in accordance with the procedures.
• Monitor the Underground installations; check the required burial depth and spacing requirements to adjacent installations, prior to back filling.
• Inspection of Electrical Installation Panels monitoring control panel wiring, termination, cable routing and cable tray installation.
• Verify all required Inspection Report and test records are systematically generated and compiled according to the QC procedures.
• Coordinate with client representatives regarding the implementation and quality of works.
• Inspection of Switchgear Panel Installation, Cable termination and Bus Bar torque.
• Installation of Control Panel marshaling panels and termination continuity and Megger test.
• Inspection of Ground Rod and Grounding Cable, as per Engineering specification.
• Preparation of Electrical Inspection Reports.
• Inspection of Heat Tracing Panel Installation, PT, RTD junction box installation and heat tracing cable laying and Meggering.
• Provide sufficient feedback to QA/QC manager on the day to day quality issues.
• To supervise and carry out effective implementation of work schedule to clear punch list.
Project: SMART FIELD MV EQUIPMENT REPLACEMENT-(SRMU)
Client: SAUDI ELECTRICITY COMPANY
• Assure the Quality Standards as per project Specifications.
• To Prepare Construction Quality Procedure and Method of Statements.
• Inspecting & supervising the smart RMU & installation work as per define method of statement as per compliance of Saudi Electric Company’s technical specification and standards.
• To understand the specifications and Engineering Reference Documents (ERD’s) and to Implement at the work site for achieving a Good Quality Work.
• Verify all the Checklists Before and After construction works.
• Preparation and Submittal for RMI and RFI.
• Review and Inspection of all Electrical Material, prior to construction works.
• Daily monitoring the Construction Activities.
• Responsible for the over-all implementation of Quality Control related electrical works in accordance with project specifications and Engineering Standards.
• Reporting weekly Progress report to QA/QC Manager.
• Issue NCR for any type of NON- CONFIRMITIES Observed.
• Attending monthly meetings with Project Team and improve all Quality Standards.
• Verify all required inspection report and test records are systematically generated and compiled according to the approved QC Procedures.
• Provide sufficient feedback to QA/QC Manager on the day to day quality issues.
• Monitoring the quality with Al Gihaz internal “Quality Management tracking system” and preparing weekly QMTS reports.
• Supervised Electrical Smart RMU installation work & tests and submitted reports to Saudi Electric Company for approval.
• Supervising RMU installation & T&C for compliance of Saudi Electric Company’s technical comments.
Project: Installation & Maintenance of Fire Alarm System in Al-Adl BSP Substation 380KV, Service building.
Client: SAUDI ELECTRICITY COMPANY
Engineering
MS-word
MS-Excel
Basic Auto-CAD
Personal Details:
Name: SYED ANAS QUADRI
Marital Status: Married
Nationality: Indian
Driving License: Valid KSA driving license
DOB: 02-08-1992
Iqama status: transferable
Mob no: 0533813487
email: s.anasquadri92@gmail.com
ISO 9001:2015 (QMS) Internal Audit Training
Workshop on MATLAB and SIMULINK & its Applications
Electrical - MEP ( Designing & Draughting ) - TAIBA ENGINEERING CONSULTANTS
Participated in Training program on Maintenance of 33/11KV substation conducted by APCPDCL.
Industrial Automation Training - AUTOMATION CONTROL SYSTEMS
Participated in Training program on Maintenance of 33/11KV substation conducted by APCPDCL.