19 years of experience ( Egypt, KSA) in Extra high voltage electrical projects Substation, OHTL, UGC, existing substation operations, maintenance, expansion ,involved in construction, testing and commissioning and rollout in the project
On notice period of resignation
Achievements/ Tasks
develop project objective by reviewing project charter, project contract and scope of work
Handling Close Out Projects work (Outages , Punch list clearance, Complete the energization of the rest of the projects equipment, deliver Spare parts, As Built )
Develop project objectives by reviewing project contract and scope of work
verification the projects deliverable issued PAC, FAC certificate
raise project change request for non conformance work
review and issued the projects invoice based on icache flow
Projects :
1-SAOO Project 2-Hajer/Nuzha 3- New Qatif 115kv 4-UQAIR A, B SS 115/13.8kv 5- FOODAH SS 115/13.8KV 6- Maritime SS 115/13.8KV
7-Abquiq_3 SS 115/13.8 KV
8-Dammam North BSP 380 /115 /13.8 KV
Achievements /Tasks
work with senior management to defined the initial scope identification
Review and revise the overall master schedule to achieve delivery time for the project
Coordinate existing lines outage work with PCC, AMD, Saudi Armco
Review contractor submittal and follow the concerned department
Handle the project stake holders meeting
Responsible and received the work permits on sites (LOA, STW, SFT)
Review and send energization documents
Project
Upgrade the OHTL and protection panels for 41 lines feeding Saudi Armco facilities Plants in 4Nos Area (UTHMANYIAH , AINDAR , SHADGUM , HAWYAH )
Achievements / Tasks
Witness all project activities
Solve technical issues with testing engineer at site
Check scheme function for all project components (GIS, Transformers, Relays, Battery, line, SAS, Telecom)
Implement Relay(OC, Dist, DiFF, DEF) setting
Fault investigation
Review and issue energization clearance
Projects
A lot of projects at Makkah like (Makkah central BSP, El Mashaar BSP, South Aziziah, Al Zahra 2, BAHRA 2,....)
@Ryadh SS like (El Narges, 9007 BSP PP7,..)
Achievements/Tasks
review design submittal include base design schematics drawings, structure design
inspection contractor incoming materials as per SEC standard and specification
Project progress meeting with contractor to ensure achieving planned milestone
issued the action plan of project problems
Carry out all projects safety requirements with contractor
Projects
1-PNU BSP 9024 SS
2-New Hateen 9005 BSP SS
3-Alorajah BSP 9016
4-Khashm Alaan 9017 BSP
Operation of 11 Nos Substation 220/66/11 KV
Transforms& CB & Swgr, Battery bank maintenance
testing transformer, CT, VT, CB, auxiliary transfer.
Projects
Qassassen66/11kv SS , North ismailia SS, kantara west 66/11Kv
Electrical power and Machine